Jack-up Gantry Lowers Tunnel Boring Machine for Paris Metro Extension
Customer
Scales SAS
Location
Paris, France
Products
JS250 Jack-up Gantry System
Challenge
The Paris Metro Line 14 South extension required the safe and precise handling of an 880-ton tunnel-boring machine within a demanding construction environment. Scales SAS needed a reliable lifting solution capable of raising and lowering the machine during the different stages of the project.
Solution
Leading French heavy lift company, Scales SAS, has used an Enerpac JS-250 Jack-up gantry system to lift and lower Koumba, a 8.9m diameter and 11.4m long tunnel-boring machine weighing 880 tons, in the latest phase of the Paris Metro extension project.
Paris Metro - Extension of Line 14 South:
Construction: L14 Sud – Lot GC04
Metro Line owner: RATP (Régie Autonome des Transports Parisiens)
Project Management: ELIOS – Groupement SETEC TPI (Mandataire) – SYSTRA
Main contractor: Groupement NGE-GC (Mandataire) – SALINI – IMPREGILO.